For a work order, standard time and time taken are 20 hours and 15 hours respectively. Time rate being Rs. 2 per hour, total wages payable under Rowan Premium Plan will be:
A.
40
B.
37.50
AnswerC.
35
D.
None of these
Answer: Option B