Q242

For providing a raft foundation, the following activities are involved i) Ramming the foundation bed ii) Excavation of the soil upto required depth iii) Laying the reinforcement over the foundation bed iv) Curing the cement concrete placed over reinforcement v) Pouring the cement concrete over the reinforcement The correct sequence is

A.
i, ii, iii, iv, v
B.
v, iv, iii, ii, i
C.
ii, i, iii, v, iv
Answer
D.
iii, ii, v, i, iv

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board