Q77
For walls, columns and vertical faces of all structural members, the form work is generally removed after
A.
24 to 48 hours
AnswerB.
3 days
C.
7 days
D.
14 days
Answer: Option A
Solution
Answer: Option A
No explanation is given for this question Let's Discuss on Board