Four gardeners with four grass mowers mow 400 sq. m of ground in 4 hours. How long would it take for eight gardeners with eight grass mowers to mow 800 sq. m of ground ?

A.
4 hours
Answer
B.
6 hours
C.
8 hours
D.
12 hours

Answer: Option A

Solution

Answer: Option A
Solution:
Since each gardener would work with one grass mower,
So, we shall consider 1 gardener and 1 grass mower as one unit.
Let the required time be x hours
More gardeners and grass mowers, Less time (Indirect proportion)
More area, More time (Direct proportion)
\left. \begin{gathered} {\text{Gardeners & grass mowers 8}}:4 \hfill \\ \,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,\,{\text{Area 400}}:800 \hfill \\ \end{gathered} \right\}::4:x