Electrical Engineering · Q76

Economics Of Power Generation

Engineering and GATE · Electrical Engineering · question 76

Q76

High load factor indicates

A.
cost of generation per unit power is increased
B.
total plant capacity is utilised for most of the time
Answer
C.
total plant capacity is not properly utilised for most of the time
D.
none of the above

Answer: Option B

Solution

Answer: Option B