If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then the same piece of work will be done by 1 man, 1 woman and 1 boy in:
A.
48 days
AnswerB.
36 days
C.
45 days
D.
50 days
Answer: Option A
Solution
Answer: Option A
Solution:
Work done by 2 men = 3 women = 4 boys1 man = 2 boys
1 woman = boys
Thus,
Boys × days = 4 × 52 boys × days
Again,
1 man + 1 women + 1 boys,
boys
Using work equivalent method,
boys × day = BOYS × DAYS
x = 48 days