Q144
If actual cost is 356000 and flexible budget cost is 255000, then flexible budget variance will be
A.
$104,000
B.
$103,000
C.
$101,000
AnswerD.
$102,000
Answer: Option C
Solution
Answer: Option C
Solution:
Flexible budget variance = Actual cost - Flexible budget cost = 255000 = $101,000.