Q187

If actual result is 65000 and static budget variance is 35000, then static budget amount will be

A.
$30,000
Answer
B.
$100,000
C.
$200,000
D.
None of the above

Answer: Option A

Solution

Answer: Option A
Solution:
Static budget amount = Actual result - Static budget variance
= 35000 = $30,000.