Q245
If an activity has zero slack, it implies that
A.
it lies on the critical path
AnswerB.
it is a dummy activity
C.
the project is progressing well
D.
none of the above
Answer: Option A
Solution
Answer: Option A
No explanation is given for this question Let's Discuss on Board