If an activity has zero slack, it implies that

A.
it lies on the critical path
Answer
B.
it is a dummy activity
C.
the project is progressing well
D.
none of the above

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board