Q338
If an actual result in static budget is 2500 and corresponding budgeted amount is 2200, then static budget variance will be
A.
$3,000
B.
$300
AnswerC.
$4,700
D.
$4,500
Answer: Option B
Solution
Answer: Option B
Solution:
Static budget variance = Static budget - Corresponding budgeted amount = 2200 = $300.