Management · Q158

Management Accounting

Graduate and Post Graduate · Management · question 158

Q158

If budgeted price of input is 70, actual quantity of input is 250 units and allowed budgeted quantity of input is 90 units, then efficiency variance will be

A.
$23,800
B.
$11,200
Answer
C.
$12,200
D.
$13,200

Answer: Option B

Solution

Answer: Option B
Solution:
Efficiency variance = (Actual quantity of input - Budgeted quantity of input) × Budgeted price of input
= (250 - 90) units × 11,200.