Q650
If budgeted total direct labour hours are 5500 and budgeted direct labour cost is 755000, then budgeted direct labour cost rate is
A.
$138 per labour hour
B.
$137.27 per hour
AnswerC.
$140 per labour hour
D.
$142 per labour hour
Answer: Option B
Solution
Answer: Option B
Solution:
Budgeted direct labour cost = Budgeted direct labour cost ÷ Budgeted total direct labour hours = 137.27 per hour