If direct material cost is 5500 and prime cost is 25000, then direct manufacturing labour would be
A.
$19,500
AnswerB.
$30,500
C.
$45,500
D.
$22,500
Answer: Option A
Solution
Answer: Option A
Solution:
Direct manufacturing labour = Prime cost - Direct material cost = 5500 = $19,500