If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good

A.
EF = ES + D
B.
LS = LFD
C.
LF = LS + D
D.
All of the above
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good
- EF = ES + D
- LS = LFD
- LF = LS + D