If flexible budget amount is 27000 and flexible budget variance is 12000, then actual result amount would be

A.
$27,000
B.
$15,000
C.
$39,000
Answer
D.
$49,000

Answer: Option C

Solution

Answer: Option C
Solution:
Actual result = Flexible budget amount + Flexible budget variance
= 12000 = $39,000