Management · Q78

Management Accounting

Graduate and Post Graduate · Management · question 78

Q78

If manufacturing cycle efficiency is 0.725 and total manufacturing time is 45 minute, then value added manufacturing time will be

A.
42.625
B.
36.724
C.
32.625
Answer
D.
41.625

Answer: Option C

Solution

Answer: Option C
Solution:
Value added manufacturing time = Manufacturing cycle efficiency × Total manufacturing time
= 0.725 × 45
= 32.625.