Q505
If sales budget variance for operating income is 68000 and static budget amount is 19000, then flexible budget amount will be
A.
$47,000
B.
$57,000
C.
$87,000
AnswerD.
$97,000
Answer: Option C
Solution
Answer: Option C
Solution:
Flexible budget amount = Operating income + static budget = 19000 = $87,000