If sales budget variance is 57000 and flexible budget amount is 97000, then static budget amount will be

A.
$40,000
Answer
B.
$154,000
C.
$164,000
D.
$124,000

Answer: Option A

Solution

Answer: Option A
Solution:
Static budget = Flexible budget - Sales budget variance
= 57000 = $40,000