Q1337
If the time is not the essence of the contract the failure to perform the contract by the specified time makes the contract
A.
Void
B.
Voidable at the instance of the promisee
C.
Remains valid but the promisee can claim compensation for the loss suffered by him by such failure
AnswerD.
Remains valid & can be performed at any subsequent time without being liable for the loss suffered by the promisee
Answer: Option C
Solution
Answer: Option C
No explanation is given for this question Let's Discuss on Board