If TL is the largest allowable event occurrence time, total activity slack (s) is equal to

A.
Latest start time earliest start time
B.
Latest finish time earliest finish time (EFT)
C.
TLEFT
D.
All of the above
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
- Latest start time earliest start time
- Latest finish time earliest finish time (EFT)
- TLEFT