Civil Engineering · Q39

Waste Water Engineering

Engineering and GATE · Civil Engineering · question 39

Q39

In a grit chamber of a sewage treatment plant,

A.
Flow velocity 0.15 m to 0.3 m/sec is kept
B.
Depth of 0.9 m to 1.20 m is kept
C.
One minute of detention period is kept
D.
All the above
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board