In a PERT chart

A.
All activities should be numbered
Answer
B.
Only important activities should be numbered
C.
Only critical activities are numbered
D.
Only selected activities are numbered

Answer: Option A

Solution

Answer: Option A
Solution:
In a PERT chart All activities should be numbered