Q183
In budget hierarchy, material handling cost is
A.
fixed manufacturing cost
B.
batch level cost
AnswerC.
per unit cost
D.
factory overall cost
Answer: Option B
Solution
Answer: Option B
Solution:
In budget hierarchy, material handling cost is batch level cost. A batch-level cost is a cost related to a group of units, but which is not associated with specific individual units.