In budget hierarchy, material handling cost is

A.
fixed manufacturing cost
B.
batch level cost
Answer
C.
per unit cost
D.
factory overall cost

Answer: Option B

Solution

Answer: Option B
Solution:
In budget hierarchy, material handling cost is batch level cost. A batch-level cost is a cost related to a group of units, but which is not associated with specific individual units.