Vidyalelo
Civil Engineering · Q70

Tunnel Engineering

Engineering and GATE · Civil Engineering · question 70

Q70

In case of drift method of tunnelling, the drift may be excavated at

A.
The centre
B.
The top or bottom
C.
The side
D.
All of the above
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board