Vidyalelo
Electrical Engineering · Q22

Electrical Cables

Engineering and GATE · Electrical Engineering · question 22

Q22

In congested areas where excavation is expensive and inconvenient 'draw in system' of laying of underground cables is often adopted.

A.
Yes
Answer
B.
No

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board