Q256
In crash program for a project
A.
both direct and indirect costs, increase
B.
indirect costs increase and direct costs decrease
C.
direct costs increase and indirect costs decrease
AnswerD.
cost is no criterion
Answer: Option C
Solution
Answer: Option C
Solution:
In crash program for a project direct costs increase and indirect costs decrease