Q90

In development headings, what is typically installed immediately after blasting and scaling?

A.
Power cables
B.
Air duct
C.
Ground support system
Answer
D.
Rail track

Answer: Option C

Solution

Answer: Option C
Solution:
Ground support system like rock bolts or mesh is applied right after cleaning.The correct answer is: Ground support systemThis ensures worker safety and tunnel stability.Other installations follow once safety is ensured.