In permanent lining, in hard rock the excavation reduced to finished diameter of the shaft and continuous thus for . . . . . . . . below.

A.
1 - 2 m
B.
2 - 3 m
C.
3 - 4 m
Answer
D.
4 - 5 m

Answer: Option C

Solution

Answer: Option C