In PERT analysis, critical path is obtained by joining events having

A.
+ve slack
B.
-ve slack
C.
Zero slack
Answer
D.
Dummy activities

Answer: Option C

Solution

Answer: Option C
Solution:
In PERT analysis, critical path is obtained by joining events having Zero slack