Q40
In PERT analysis, the expected time to complete an activity is computed from the three time estimates : a most likely time (m), an optimistic time (a), and pessimistic time (b) using the expression
A.
Answer
B.
C.
D.
Answer: Option A
Solution
Answer: Option A
No explanation is given for this question Let's Discuss on Board