Vidyalelo
Mining Engineering · Q17

Mine System Engineering

Engineering and GATE · Mining Engineering · question 17

Q17

In PERT network, the activity duration is assumed to follow

A.
Beta distribution
Answer
B.
Normal distribution
C.
Binomial distribution
D.
Weibull distribution

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board