Vidyalelo
Mining Engineering · Q35

Mine System Engineering

Engineering and GATE · Mining Engineering · question 35

Q35

In the project network shown activity durations are given in months. If the activity can be crashed to expedite the project, which one would you crash and by how many months?

In the project network shown activity durations are given in months. If the activity can be crashed to expedite the project, which one would you crash and by how many months?
Mine System Engineering mcq question image
A.
C, 1
Answer
B.
C, 2
C.
D, 1
D.
E, 1

Answer: Option A

Solution

Answer: Option A
No explanation is given for this question Let's Discuss on Board