Vidyalelo
Civil Engineering · Q27

Tunnel Engineering

Engineering and GATE · Civil Engineering · question 27

Q27

In the wooded bulk-head, used for mucking in steep grade tunnels,

A.
One opening is provided
B.
Two openings are provided
Answer
C.
Three openings are provided
D.
No opening is provided

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board