Vidyalelo
Civil Engineering · Q4

Engineering Economics

Engineering and GATE · Civil Engineering · question 4

Q4

Keeping in view, the feasibility order of magnitude, the preliminary, conceptual or budget estimates, are prepared by:

A.
Architect/engineer
B.
Construction manager
C.
Owner himself/herself
Answer
D.
None of the above

Answer: Option C

Solution

Answer: Option C
No explanation is given for this question Let's Discuss on Board