Vidyalelo
Mechanical Engineering · Q196

Engineering Materials

Engineering and GATE · Mechanical Engineering · question 196

Q196

Lead is poured into the joint between two pipes. These pipes may be made of

A.
Cast iron
Answer
B.
Vitrified clay
C.
Asbestos cement
D.
Concrete

Answer: Option A

Solution

Answer: Option A
Solution:
Lead is poured into the joint between two pipes. These pipes may be made of Cast iron
Cast iron has a much higher melting point than lead.