Match the following. List-I List-II a. Project schedule development 1. Specifying budgeted cost to be incurred at the completion of project. b. Budget planning 2. Listing the entire schedule of activities. c. Quality planning 3. Who will do what work at which time. d. Resource planning 4. Assessing quality criteria used for project

Match the following.
List-I List-II
a. Project schedule development 1. Specifying budgeted cost to be incurred at the completion of project.
b. Budget planning 2. Listing the entire schedule of activities.
c. Quality planning 3. Who will do what work at which time.
d. Resource planning 4. Assessing quality criteria used for project
A.
a-2, b-1, c-4, d-3
Answer
B.
a-4, b-3, c-2, d-1
C.
a-1, b-2, c-3, d-4
D.
a-2, b-4, c-1, d-3

Answer: Option A

Solution

Answer: Option A