Vidyalelo
Commerce · Q942

Costing

Graduate and Post Graduate · Commerce · question 942

Q942

Match the following. List-I (Variances) List-II (Causes) a. Overhead efficiency variance 1. Power failure b. Overhead volume variance 2. Appointing low grade employees c. Labour idle time variance 3. Poor working condition d. Labour efficiency variance 4. Working days being more or less than budgeted

Match the following.
List-I (Variances) List-II (Causes)
a. Overhead efficiency variance 1. Power failure
b. Overhead volume variance 2. Appointing low grade employees
c. Labour idle time variance 3. Poor working condition
d. Labour efficiency variance 4. Working days being more or less than budgeted
A.
a-4, b-3, c-2, d-1
B.
a-3, b-4, c-1, d-2
Answer
C.
a-3, b-1, c-4, d-2
D.
a-2, b-1, c-4, d-3

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board