Q1097
Material price variance is the difference between standard and actual prices of materials used multiplied by . . . . . . . .
A.
Actual quantity of materials used
AnswerB.
Budgeted quantity of materials used
C.
Standard quantity of materials used
D.
Either A or B
Answer: Option A
Solution
Answer: Option A
No explanation is given for this question Let's Discuss on Board