One of the basic essentials of an incentive plan is that

A.
A differential piece rate system should exist
B.
Minimum wages should be guaranteed
C.
Provide incentive to group efficiency performance
D.
All standards should be based on time studies
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
One of the basic essentials of an incentive plan is that All standards should be based on time studies