Engineering and GATE · Mechanical Engineering · question 238

Q238

PERT

A.
Provides an approach for keeping planning up-to-date
B.
Provides a way for management to require that planning be done on a uniform and logical basis
C.
Permits management to foresee quickly the impact of variations from the plan
D.
All of the above
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
PERT
- Provides an approach for keeping planning up-to-date
- Provides a way for management to require that planning be done on a uniform and logical basis
- Permits management to foresee quickly the impact of variations from the plan