Mechanical Engineering · Q241

Industrial Engineering And Production Management

Engineering and GATE · Mechanical Engineering · question 241

Q241

PERT is the

A.
Time oriented technique
B.
Event oriented technique
Answer
C.
Activity oriented technique
D.
Target oriented technique

Answer: Option B

Solution

Answer: Option B
Solution:
PERT is the Event oriented technique