Vidyalelo
Mechanical Engineering · Q243

Industrial Engineering And Production Management

Engineering and GATE · Mechanical Engineering · question 243

Q243

PERT stands for

A.
Program Estimation and Reporting Technique
B.
Process Estimation and Review Technique
C.
Program Evaluation and Review Technique
Answer
D.
Planning Estimation and Resulting Technique

Answer: Option C

Solution

Answer: Option C
Solution:
PERT stands for Program Evaluation and Review Technique