PERT/CPM, techniques can be used for following applications

A.
Once through project
B.
Maintenance jobs
C.
Research and development
D.
All of the above
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
CPM is a statistical technique of project management in which planning, scheduling, organising, coordination and control of well-defined activities take place. PERT is a technique of planning and control of time.