Pick up the correct statement from the following:

A.
The pile driven in sand is called sand pile
Answer
B.
The drilled hole filled with sand is called sand pile
C.
The sand piles are used for bearing purposes
D.
None of these

Answer: Option A

Solution

Answer: Option A