Vidyalelo
Civil Engineering · Q187

Building Construction

Engineering and GATE · Civil Engineering · question 187

Q187

Pick up the incorrect statement from the following:

A.
Horizontal D.P.C. is provided at plinth level in internal walls
B.
D.P.C. is provided under door and verandah openings
Answer
C.
Vertical D.P.C. is not provided in internal walls
D.
Cement concrete is a rigid damp-proofing material

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board