Vidyalelo
Mechanical Engineering · Q267

Industrial Engineering And Production Management

Engineering and GATE · Mechanical Engineering · question 267

Q267

Pick up the incorrect statement from the following

A.
An activity of the project is denoted by an arrow on the net work
B.
The tail of the arrow indicates the start of the activity
C.
The head of the arrow indicates the end of the activity
D.
The arrows are drawn (to scale from) left to right
Answer

Answer: Option D

Solution

Answer: Option D
Solution:
- An activity of the project is denoted by an arrow on the net work.
- The tail of the arrow indicates the start of the activity.
- The head of the arrow indicates the end of the activity.