Portion of labour costvariance which is due to the difference between predetermined working days and actual working days is

A.
labour idle time variance
B.
labour calender variance
Answer
C.
labour rate variance
D.
labour efficiency variance

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board