Q276
Positive slack on a PERT indicates that project is
A.
Ahead of schedule
AnswerB.
Beyond schedule
C.
As per schedule
D.
On critical path
Answer: Option A
Solution
Answer: Option A
Solution:
A positive slack indicates the amount of time that the task can be delayed without delaying the project finish date.