Select the correct statement.

A.
Quantity of binder required for tack coat is less than that required for prime coat.
B.
Prime coat treatment is given for plugging the voids in water bound macadam during bituminous road construction.
C.
Seal coat is the final coat over certain previous bituminous pavements.
D.
A bitumen primer is a high viscosity cutback.
Answer

Answer: Option D

Solution

Answer: Option D
No explanation is given for this question Let's Discuss on Board