Vidyalelo
Civil Engineering · Q23

Docks And Harbor Engineering

Engineering and GATE · Civil Engineering · question 23

Q23

Select the incorrect statement.

A.
The progress of work in low level method of mound construction is very slow
B.
Barge method of mound construction is economical
Answer
C.
In low level method of mound construction, the area of working is limited
D.
In staging method of mound construction, the work is not interrupted even during stormy weather

Answer: Option B

Solution

Answer: Option B
No explanation is given for this question Let's Discuss on Board